project
- The customer on a project tells the project manager he has run out of money to pay for the project . What should the project manager do FIRST ?
- During the project,a team member tells you that a major risk identified by the team has occurred.However,it is not as serious as previously thought.What is the FIRST thing you should do?
- Your project,run for a customer,is coming to an end.The customer has been contractually granted a three years warranty period for the product of the project.What should the project manager do first?
- n terms of the budget,the project manager must report to the sponsor on the value of the work performed to date.What should the project manager calculate?
- Which of the following configuration management activities is part of the Perform Integrated Change Control Proces?
- The project team finds that the project is likely to be exposed to significant financial risk.What strategy should be used to manage this type of risk?
- The director of the business unit submits a request for a new software application.The project manager determines the need for project requirements gathering and scope development.Which of the following should the project manager be performed?
- The project manager can enhance project communication and team building by doing all the following except—
- The Project Life Cycle:
- Maintenance and on-going operations are crucially important to projects and should: