• 登陆
  • 注册
  • SiteMap

正确答案网

  • 正确答案网
  • 医学
  • 国民教育
  • 财经
  • 驾考
  • 教师资格证
  • 考研
  • 公务员
  • 正确答案网
  • 执业考试
  • 项目管理师
问题

n terms of the budget,the project manager must report to the sponsor on the value of the work performed to date.What should the project manager calculate?

A:Actual costs
B:Planned valu
C:Earned valu
D:Variance analysis.
正确答案是:
标签: manager , project , terms
同类题型

For which of the following can the work breakdown structure be used?

如果项目A的净现值为30000美元,项目B的为50000美元,那么选取B的机会成本是多少?()

一名团队成员在项目执行阶段报告了一个之前被记录为一个风险的问题,项目经理下一步应该怎么做

The BCWS=$250, the ACWP=$350, and the BCWP=$200, Calculate the Cost Variance

Which of the following terms describes the strong pressures within a group to conform to group norms at the expense of critical and innovative thinking?

  • 友情链接:
  • markdown
  • 坚果云
  • listary中文网
  • 柿皮网
  • IDM
  • 坚果云扫描
  • Fences中文网
  • Office教程
考试答案、作业答案,找答案就上正确答案网!
www.zhengquedaan.cn版权所有 ©2020-2025 沪ICP备2020036959号-5