During the project,a team member tells you that a major risk identified by the team has occurred.However,it is not as serious as previously thought.What is the FIRST thing you should do?
                            A:Increase the quality standard.
B:Present this finding to the project team and ask them to verify the team member’s finding.
C:Investigate changing the contingency plan
D:Notify management.
                        
                        B:Present this finding to the project team and ask them to verify the team member’s finding.