问题
                    
To integrate approved scope changes, the PM should begin with:
                            A:Approved budget
B:Project schedule
C:Human resource requirements
D:Product descriptionE.WBS
                        
                        B:Project schedule
C:Human resource requirements
D:Product descriptionE.WBS