A project of 2 million has an adverse event that has the probability of 50% of occurrence and a potential loss of $20,000. This represents an expected negative value of:
提交标书或建议书之前,一家公司与所有潜在卖方开会。公司希望确保所有潜在卖方采购流程有一个明确的共识。该公司正处于下列哪一项采购管理过程组中
你是东西建筑公司的项目经理。在完成建筑后,你到实施地点检查是否建筑按照计划进行了测量。这是什么的例子?
The construction phase of a new software product is near completion .The next phase is testing and implementation. The project is two weeks ahead of schedule. What should the project manager be MOST concerned with before moving onto the final phase?
假设实际成本是$计划价值是$挣值是$根据这些数据可确定有关进度偏差的哪些信息?