• 登陆
  • 注册
  • SiteMap

正确答案网

  • 正确答案网
  • 医学
  • 国民教育
  • 财经
  • 驾考
  • 教师资格证
  • 考研
  • 公务员
  • 正确答案网
  • 执业考试
  • 项目管理师
问题

The total amount of risk that is calculated for a project is found by:

A:Multiplying the sum of each the risks times the amount at stake
B:Calculating the cumulative sum of the probability for each risk and multiplying this value times the consequence of occurrence of the risk events
C:Cannot be calculated since all risks are not known
D:The amount of project reserves available
正确答案是:
标签: amount , calculated , risk
同类题型

The sponsor and other in your organization are repeatedly requesting changes . When you try to implement some of the changes, you discover the current contract does not include a budget for evaluating changes . What should you do?

你管理着一个电子设备的项目, 需要建立了一个变更控制委员会来负责项目变更建议的审查和处理工作。在你立这个委员会的时候,你还确立了支配起运作的具体程序和规则。这个程序要求所有得到批准的变更都要在下列哪一项中得到反映()

你在加拿大的某省工作,按照合同应每天到政府事务办公室去。上个月因为大风雪天气你有3天没去。你的缺席是可被接受的,因为合同中有如下的条款——()

项目经理接管客户一个发展良好的项目。该项目是一个由外部资助的项目,实行严格的付款计划和期限。在项目实施阶段,项目经理确定该项目工期落后了,此时项目经理应该怎么做?

质量可被定义为 ()

  • 友情链接:
  • Office教程
  • 坚果云
  • Fences中文网
  • 坚果云扫描
  • IDM
  • listary中文网
  • 柿皮网
  • markdown
考试答案、作业答案,找答案就上正确答案网!
www.zhengquedaan.cn版权所有 ©2020-2025 沪ICP备2020036959号-5