The total amount of risk that is calculated for a project is found by:

A:Multiplying the sum of each the risks times the amount at stake
B:Calculating the cumulative sum of the probability for each risk and multiplying this value times the consequence of occurrence of the risk events
C:Cannot be calculated since all risks are not known
D:The amount of project reserves available