A project manager is managing a project and at present is organizing group activities to document the project demand baseline from that project.Which the following techniques that the project manager can be used?
You are the project manager for a large project under contract with the government . The contract for this two year , multi-million dollar project was signed six months ago. You were not involved in contract negotiations or setting up procedures for manag
你在管理一个为50岁以上的人开发一种以黄豆子基础的富含镁元素的营养饮料项目。你最近听到客户将你的进度报告称做“古巴比伦国王的密码”,似乎它们是用象形文字写成的,除了埃及考古学者以外没有人能读懂。这种情况能通过什么来避免? ()
项目经理了解到一项变更请求已获批准,这项变更将影响到项目成本和项目进度。项目经理应该怎么做
你负责管理一个数据中心 建设 项目,涉及到10个主要干系人,他们分别代表7个大公司。这个大项目涉及到物业、装修、强电、弱电、计算机硬件、系统软件、系统集成和 IT 咨询等8个不同的承包商,他们的工作必须相互协调。你直接管理的项目团队有六个团队领导。每个团队领导各带领一支由7人组成的团队。因此,你认识到必须投入大量的精力进行有效的整体变更控制。这意味着你主要关心:()