Which of the following is true?
A:An experienced Project Manager will avoid projects that contain uncertainty .
B:There can be a project life cycle stage before the actual decision and approval to proceed with the project .
C:Risk is always highest towards the end of a project when time is running out .
D:A project doesn't really finish because the product and / or services that were delivered need supporting .
B:There can be a project life cycle stage before the actual decision and approval to proceed with the project .
C:Risk is always highest towards the end of a project when time is running out .
D:A project doesn't really finish because the product and / or services that were delivered need supporting .
正确答案是: