Which of the following needs to be completed before resources can be finalized for the project?
                            A:Work breakdown structur
B:Estimates.
C:Resource Gantt Chart.
D:Scope Verification.
                        
                        B:Estimates.
C:Resource Gantt Chart.
D:Scope Verification.