The project manager leads a development project for the customer.The project is externally funded with a strict payment plan and deadline.During the project execution phase,the project manager identifies that the project is behind schedule.What should the project manager do?

A:Perform schedule compression to reach the determined deadline.
B:Issue a change request and approve it with the customer.
C:Take no action,since the contract does not identify penalties for late product deliverables.
D:Decrease the number of quality audit to make the delivery on tim