Which one of the following is NOT a trade-off decision that must be made in the development of the project plan?
The project team finds that the project is likely to be exposed to significant financial risk.What strategy should be used to manage this type of risk?
在进行成本估计时,你必须考虑直接成本、间接成本、一般管理成本和总的管理成本。以下哪一个不是直接成本?()
应急计划编制包括 ()
有关工作先后次序安排的工具和方法有几种,究竟选择何种工具和方式取决于很多因素。如果项目经理决定选用子网络或分网络作为他的或她的进度安排技术,该项目:()