While preparing your risk responses, you realize that you have not planned for know risk events . You need to make adjustments to the project to compensate for unknown risk events . These adjustments are based on your past project experience when unknown

A:Apply a general contingency to try to compensate .
B:Document the unknown risk items and calculate the expected monetary value based on probability and impact that result from the occurrence .
C:Determine the unknown risk events and the associated cost, then add the cost to the project budget as reserves .
D:Add a 10% contingency .