Management tells a project manager to subcontract part of the project to a company that management has worked with many times . Under these circumstances, the project manager should be MOST concerned about:

A:making sure the company has the qualifications to complete the project .
B:meeting management expectations of time .
C:the cost of the subcontracted work .
D:the contract terms and conditions .