项目经理怀疑一名团队成员严重影响到其他团队成员。若要避免不适当的影响,项目经理可以采用以下哪一种方法?
You are managing a two-year project involving staff from several departments . The project is on schedule and within budget . A key team member leaves for a four-week vacation without completing a highly technical and specialized task assigned to him (tas
重要的项目干系人质疑项目基准的有效性,经过长时间讨论,仍然无法达成一致。项目经理应该如何做?()
对项目来说,暂时的意思是:()
最高风险影响通常发生在项目生命周期的哪些阶段? ()