问题

A project manager in a predominantly hierarchical organization has been assigned a major project with aggressive timelines . The BEST approach for developing an initial project charter in this environment is to :
A:create a charter using brainstorming sessions with potential team members and stakeholders .
B:create and present a draft project charter to potential team members and stakeholders to solicit their input .
C:create a project charter jointly with the project sponsor for distribution to potential team members and stakeholders .
D:create a charter with the functional managers and present it to the sponsor for signature .
B:create and present a draft project charter to potential team members and stakeholders to solicit their input .
C:create a project charter jointly with the project sponsor for distribution to potential team members and stakeholders .
D:create a charter with the functional managers and present it to the sponsor for signature .
正确答案是: