问题

The role of each stakeholder is determined by:

A:the stakeholder and the sponsor .
B:the project manager and the sponsor .
C:the team and the project manager .
D:the project manager and the stakeholder .
正确答案是:
标签: manager , project , stakeholder
同类题型

A project manager who wants to create a receptive atmosphere for communicating should

Your organization is having a difficult time managing all of its project . You have been asked to help senior management get a better understanding of the problems . What do you do FIRST?

无成本解决有时用于:()

检验项目工作是否完成,需要使用:()

以下哪项因为允许对工作进行系统评估所以在识别风险时非常有用? ()