During the execution phase of the project, you realized the subcontractors are working with incomplete and different scope statements. As the project manager, what should you do FIRST?

A:Check the work completed against the correct scope statements。
B:Review the scope of work with the stakeholders。
C:Document the inconsistencies to management,calculating the cost of non-conformance
D:Stop all activities until the scope of work is complete。