The Program Evaluation and Review Technique (PERT) is a method of scheduling projects. In the context of risk, PERT is better than the Critical Path Method because it deals with the _______ associated with ________.

A:Logic, cost estimates
B:Logic, schedule estimates
C:Certainty, cost estimates
D:Uncertainty, schedule estimatesE.Certainty, schedule estimates