The project manager establishes a risk models that will be used on the Boston project. The risk model shows the risk events and provides the probabilities of occurrence What is missing from this risk design?

A:Nothing, the risk design is complete
B:The risk probabilities need to be summed to determine the total project risk
C:The risk events must be labeled as internal or external risk events
D:The risk events do not address the technology used by the Boston projectE.The impact of the risk on the project’s objectives has not been assessed and assigned